Right here is the weekly road enchancment report for District 29: 

BRADLEY COUNTY SR-2 (US-11) resurfacing from Previous Freeway 11(LM 18.2) To close the Hiwassee River (LM 20.9): All by way of this reporting interval, the contractor Might have Daily lane closures on SR-2 (US-11) to carry out final pavement markings and to work on the punch itemizing. These closures Shall be in place from 8 AM To 5:30 PM. Motorists are suggested To Scale again velocity Inside the work zone and Look forward to flaggers aiding with visitors administration.

[Wright Brothers Construction Agency, Inc./Wagner/CNW158]

 

BRADLEY COUNTY SR-60 widening from the 4-lane north of I-75 (LM 17.2) to SR-306 (LM19.9): All by way of this reporting interval the contractor Might have brief time period intime periodittent lane closures by way ofout the enterprise for utility relocation and shifting gear as work proceeds on new roadway alignments and A mannequin new bridge over Candies Creek. Paving operations will Finish in elevated brief time period lane blockages during this reporting interval. The velocity restrict Inside the work zone has been lowered to 35 mph. Motorists are suggested To make the most of warning Inside the work zone and Look forward to flaggers aiding with visitors administration.

[Summers-Taylor, Inc./Wagner/CNV130]

 

HAMILTON COUNTY I-24 interchange enchancment at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): Williams Street is shutd to all visitors On the I-24 underpass to assist the set upation Of latest storm drainage buildings for The mannequin new frontage road. Traffic will nonetheless Be In a place to entry the ramps to I-24 and US-27, however no by way …….